This record covers batch SN-2026-09: 186 kg in nine cartons, shipped from Shanghai to Hai Phong on 18 September 2026 under CIF, arriving on 21 October after 33 days at sea.
The short answer
Sea was the right call because nothing was down. At 186 kg the air rate would have been roughly four times the freight on a batch that only had to arrive before a planned November outage.
- 186 kggross weight
- 9cartons on one pallet
- 33 daysport to port
What was in the carton
| Model | Qty | HS code | What it is |
|---|---|---|---|
| PSTX170-600-70 | 1 | 8536.50 | PSTX soft starter, 170 A |
| ACS880-01-145A-3 | 1 | 8504.40 | ACS880 drive, 145 A, 400 V |
| 6ES7416-3XS07-0AB0 | 1 | 8537.10 | CPU 416-3 PN/DP |
| 140CPU65160 | 1 | 8537.10 | Modicon Quantum CPU |
| Q06UDEHCPU | 2 | 8537.10 | MELSEC Q series CPU |
| ANB10D-425/CU2N | 1 | 8537.10 | Centum VP node unit |
Nine cartons on a single heat-treated pallet, 1.1 m x 0.9 m x 0.75 m, 0.9 m3. The ACS880 carton at 38 kg formed the base layer; the CPUs and the node unit traveled in a foam-lined carton on top, with nothing stacked above them.
How it was routed
| Decision | Chosen | Why |
|---|---|---|
| Incoterm | CIF Hai Phong | The buyer's forwarder quoted CIF and the buyer wanted the two quotes comparable; risk passes at the ship's rail in Shanghai |
| Mode | Sea LCL, consolidated in Shanghai | 0.9 m3 does not justify a 20 ft container, and the batch had five weeks of slack |
| Cut-off | 15 September, sailed 18 September | Missing the consolidation cut-off costs a week, not a day; the booking was made 12 days ahead |
| Transit | 33 days port to port | Direct call at Hai Phong, no transhipment; inland delivery was arranged by the buyer |
| Packing | 9 cartons, one heat-treated pallet | ISPM 15 stamp on two sides, photographed before the pallet was wrapped |
| Insurance | 110% of CIF value, ICC(A) | CIF obliges the seller to insure; 110% is the convention and covers the buyer's expected margin |
| Chargeable weight | 186 kg gross, 1 m3 measure | LCL charges on whichever is greater, so the packing was kept compact deliberately |
CIF is the term most often quoted by a buyer's own forwarder and the one most often misunderstood: the seller pays freight and insurance to the named port, and the risk transfers when the goods are on board, not when they arrive.
Documents issued
| Document | Issued by | Why it was needed |
|---|---|---|
| Commercial invoice | Chenfeng | CIF value, freight and insurance shown separately, which the Vietnamese agent needed for the duty base |
| Packing list | Chenfeng | Nine carton numbers against the pallet, with per-carton weights and the stack order |
| Bill of lading, 3 of 3 originals | Carrier | The buyer's agent would not release the container against a copy; see the note on the four-day gap below |
| Certificate of origin, general | CCPIT | Requested for the import file; the ASEAN-China preference needs a Form E, which the buyer did not ask for |
| Insurance certificate | Insurer | CIF requires it, and the buyer needs it on file before the container is released |
| ISPM 15 heat-treatment stamp | Pallet supplier | Vietnam enforces ISPM 15; an unstamped pallet is fumigated at destination at the importer's cost |
| Test report, one per unit | Chenfeng bench | Serial numbers and measured values, so the receiving inspection can be signed off without powering everything up |
No MSDS. Nothing in this batch is a battery, a gas cylinder or a hazardous preparation, and the soft starter and drive contain no dangerous goods for sea freight.
What happened
Why sea, and what had to stay true for it to work
The ACS880 and the soft starter were spares for a planned outage in the second week of November. Nothing was down, the plant had a date, and the batch weighed 186 kg across nine cartons. That combination is exactly when sea wins: the air rate would have been roughly four times the freight for five weeks of time nobody needed.
The condition attached to it was the cut-off. An LCL booking misses its consolidation and the batch waits a week for the next one, so the booking was placed twelve days before sailing and the pallet was packed and weighed two days before the cut-off.
The inland leg was left to the buyer deliberately. CIF ends at Hai Phong, and a delivered price to the factory would have meant using a forwarder the buyer already has a contract with. Quoting to the port kept both offers comparable.
The pallet is a document
Vietnam enforces ISPM 15, and an unstamped pallet is either refused or fumigated at the importer's expense, usually after a week of storage charges. Our pallet is heat treated, stamped on two sides, and the stamp is photographed before wrapping.
The photograph goes into the document pack, which sounds excessive until a destination inspection asks for evidence that the timber was treated. A picture taken at packing time answers that question in a minute.
The pallet was also built for the load rather than reused. 186 kg on a light pallet with a 38 kg drive at the base will deform in a shared container, and a deformed stack is how cartons arrive with crushed corners.
The four days the originals spent in the air
Three original bills of lading travel by courier. The vessel arrived on 21 October and the documents landed with the buyer's agent on the 25th, so the container sat at Hai Phong for four days with demurrage accruing against a batch that had arrived perfectly on time.
Nothing was wrong with the shipment; the term was. CIF with original B/L is the standard arrangement when a bank is involved, and this buyer pays by T/T, so the originals were a convention rather than a requirement.
For repeat buyers paying by T/T we now issue a sea waybill or ask the carrier for a telex release, which removes the courier leg entirely. Where the buyer's bank requires originals, they stay, and the four days are budgeted into the delivery date quoted.
Stacking order, and why the drive went on the bottom
The ACS880 carton weighs 38 kg and the CPUs weigh under two kilos each. Putting the heavy carton on top of a foam-lined box of controllers is how a batch arrives with bent housings and a claim that nobody can attribute.
So the drive formed the base layer on a plywood sheet, the light carton sat above it with corner blocks, and the pallet was wrapped with the carton numbers visible: 1 of 9 through 9 of 9, matching the packing list line by line.
The receiving inspection at Hai Phong took forty minutes against that list. On a batch with nine cartons and six part numbers, matching numbers on the outside is worth more than any amount of packaging description on the invoice.
Sea shipments now include a photo set of the pallet stamp, the carton labels and the sealed container number, and the bill of lading is issued as a sea waybill unless the payment terms call for originals. Both changes came out of the four days this container spent waiting for paper.
Models in this batch
Where these models sit in the catalog
-
PSTX170-600-70
Quote on request
PSTX soft starter, 170 A, the heaviest single item after the drive.
Request a price -
ACS880-01-145A-3
Quote on request
ACS880, 145 A at 400 V, the 38 kg carton that formed the pallet base.
Request a price -
6ES7416-3XS07-0AB0
Quote on request
CPU 416-3 PN/DP, a spare for the S7-400 rack that stays in service.
Request a price -
140CPU65160
Quote on request
Modicon Quantum CPU, sourced rather than stocked, which is why the batch had slack.
Request a price -
Q06UDEHCPU
Quote on request
MELSEC Q series CPU, two units for the same line.
Request a price